Transformation status
This article documents the changes when setting an application status to Complete in the Transformation Schedule.
Contents
Overview
Within Cloud Navigator, transformation or migration activities can be set against servers, databases and interfaces. This include actions like Rehost, Replatform etc. and a status such as Proposed, Planned etc.
In the Transformation Schedule, these activities can be marked as complete for applications or groups of servers. Once completed, Cloud Navigator will update the applications and servers. The effect of completing each type of activity is as per below.
This action cannot be reversed and care should be taken when using it.
Rehost
Transformation Date updates to Blank
Transformation Activity updates to the application new 7R
Transformation Status updates to Proposed
When an application is added to a new move group or a move group is archived any manfully set status’s or activities are reset back to system aligned
In Servers associated the field Data Centre updates to data previously held in Target Location
In Servers associated the Matched Machine Type is cleared
In Servers associated the Matched Machine Projected Monthly Cost is cleared
In Servers associated the VM Host is cleared
In Servers associated the field Current Number of Cores updates to values taken from Matched Machine type
In Servers associated the field Current RAM updates to values taken from Matched Machine type
In Servers associated the field Current Disk updates to values taken from Matched Machine type
In Servers associated utilisation information (Peak and Average) for CPU is cleared
In Servers associated utilisation information (Peak and Average) for RAM is cleared
In Servers associated the field Type updates to values taken from Matched Machine type
AWS = EC2 VM
Azure = Azure VM
GCP = GCP VM
Oracle = OCI VM
Replatform
Transformation Date updates to Blank
Transformation Activity updates to the application to Retain
Transformation Status updates to Proposed
In Servers associated the field Data Centre updates to data previously held in Target Location
In Servers associated the Matched Machine Type is cleared
In Servers associated the Matched Machine Projected Monthly Cost is cleared
In Servers associated the VM Host is cleared
In Servers associated the field Current Number of Cores updates to values taken from Matched Machine type
In Servers associated the field Current RAM updates to values taken from Matched Machine type
In Servers associated the field Current Disk updates to values taken from Matched Machine type
In Servers associated utilisation information (Peak and Average) for CPU is cleared
In Servers associated utilisation information (Peak and Average) for RAM is cleared
In Servers associated the field Type updates to values taken from Matched Machine type
AWS = EC2 VM
Azure = Azure VM
GCP = GCP VM
Oracle = OCI VM
Retire
Removes the Server and all details from Cloud Navigator
Refactor
Removes the Server and all details from Cloud Navigator
Repurchase
Removes the Server and all details from Cloud Navigator
Retain
No changes required - I think we need the following changes:
Transformation Date updates to Blank
Transformation Status updates to Proposed